Mermaid Gantt Chart Syntax

A Gantt chart shows tasks as bars on a timeline, with sections, dependencies and milestones. Edit the example below and the diagram redraws as you type; every example on this page can be opened in the editor.

Runs 100% in your browser — nothing is uploaded

Mermaid code
Tip: drop a file here424 chars · 424 bytes · 12 lines
DiagramRendering…

Loading Mermaid…

What a Mermaid gantt chart is for

A Gantt chart shows tasks as bars on a timeline, with sections, dependencies and milestones. Mermaid computes dates from durations and after clauses, so moving one task shifts everything that depends on it.

Gantt Chart syntax

SyntaxMeaning
dateFormat YYYY-MM-DD How dates in tasks are written
axisFormat %b %d How the axis labels dates (d3 time format)
title Text Chart title
section Name Group the following tasks
Task :t1, 2026-01-05, 3d Task with id, start date and duration (d, w, h)
Task :t2, after t1, 2d Starts when t1 ends
Task :after t1 t3, 2d Starts after several tasks
Task :2026-01-05, 2026-01-09 Explicit start and end
done / active / crit Tags before the id: finished, in progress, critical path
Release :milestone, m1, 2026-02-01, 0d Milestone (diamond)
excludes weekends Skip weekends when counting durations
todayMarker off Hide the line for today

Basic example

gantt
    title Website relaunch
    dateFormat YYYY-MM-DD
    section Design
        Wireframes        :done, des1, 2026-01-05, 5d
        Visual design     :active, des2, after des1, 7d
    section Build
        Frontend          :dev1, after des2, 10d
        Backend API       :dev2, after des1, 12d
    section Launch
        QA                :qa, after dev1 dev2, 4d
        Go live           :milestone, after qa, 0d

Open this example in the Mermaid editor

More gantt chart examples

Sprint plan excluding weekends

excludes weekends makes 5d mean five working days; crit highlights tasks on the critical path.

gantt
    title Sprint 14
    dateFormat YYYY-MM-DD
    axisFormat %b %d
    excludes weekends
    section Backend
        Payments API       :crit, api, 2026-03-02, 5d
        Webhooks           :hooks, after api, 3d
    section Frontend
        Checkout UI        :ui, 2026-03-02, 6d
        Integrate API      :crit, after api ui, 2d
    section Release
        Code freeze        :milestone, freeze, 2026-03-13, 0d

Open “Sprint plan excluding weekends” in the editor

Common mistakes

  • Task ids are optional but needed for after clauses. Without an id, a task starts when the previous one ends.
  • Tags (done, active, crit, milestone) must come before the id and dates.
  • A colon in a task name ends the name; leave colons out of task titles.

Use it in Markdown

```mermaid
gantt
    title Website relaunch
    dateFormat YYYY-MM-DD
    section Design
        Wireframes        :done, des1, 2026-01-05, 5d
        Visual design     :active, des2, after des1, 7d
    section Build
        Frontend          :dev1, after des2, 10d
        Backend API       :dev2, after des1, 12d
    section Launch
        QA                :qa, after dev1 dev2, 4d
        Go live           :milestone, after qa, 0d
```

GitHub, GitLab, Azure DevOps, Obsidian, Notion and docs generators such as Docusaurus and MkDocs (with a plugin) draw fenced mermaid blocks. Check it locally in the Markdown preview.

Other Mermaid diagrams

Sources

Spotted a mistake? Email hello@devtoolsmith.com and we’ll fix it.

Frequently asked questions

How do I start a Mermaid gantt chart?

Begin the diagram with the keyword gantt on its own line, then add one statement per line. In Markdown, wrap the whole diagram in a fenced code block with the language mermaid so GitHub, GitLab and most docs sites draw it.

How do I export a Mermaid gantt chart as an image?

Paste the diagram into the editor on this page and use SVG or PNG above the preview. SVG stays sharp at any size and can be edited further; PNG is exported at twice the screen resolution for slides and documents. Nothing is uploaded.